Week 2/6/08, bit of a wash out week, Monday we started on the waste pipes,got first manhole and pipes along front in on Monday Then Tuesday was a washout, with wednesday looking bad John decided to go home,as we where away on Thursdy and Friday anyway. Wednesday turned out fine, so I dug the waste trench down the back and restacked the beams for the floor. Week 9/6/08 More drain work, back filling with pea shingle, connecting front half of drains to existing waste pipe, needs inspecting before we can fill them in, so have to stay like this for a bit Starting the floor, beam and block, goes down quick and easily, great idea |